Diving . Rov . Corrosion Control

Subsea Inspection

TOPSIDE AND UNDERWATER PRODUCTION PLATFORM CORROSION INTEGRITY TREATMENT

Location: Ghana/ SOPC, Ghana, Sept. 2008


Scope of Work: Grit blasting to SSPC 2.5 of 12no. Can legs with concentric legs to include platform expansive Hull, to smooth bare metal without corrosion lags. 2 compound epoxy coating and polyurethane finish application by micron weight for complete cover of total areas. Coating thickness integrity test conducted. Anode retrofit of 84nos Aluminium 245kg weight through sections of up to 90fsw of can legs to sea bed.

Eradication of marine growth at weld sections and CP integrity test ith Bathycorometer of Ag/AgCl half cell.